The 2025 Street Surface Seal Project combines the 2024 and 2025 Street Surface Seal Projects focusing on Areas 5 & 1.
Phase 1 (Base Repairs) began mid-July and focused on repairing localized asphalt failures.
Phase 2 (Striping and Pavement Markings Removal and Crack Seal) will run throughout the month of August 2025 into September 2025.
Phase 3 (Surface Seal) will follow Phase 2 and run through the month of October. This phase includes:
Click the link below to explore the Surface Seal Schedule Map and view layers for the 2024 and 2025 projects.
Click below to download the detailed weekly schedule map showing planned work by street and date.
Weekly Schedule Map (PDF)(PDF, 39MB)
Weekly Schedule Excel(PDF, 83KB)
Spanish(PDF, 3MB)
Tagalog(PDF, 3MB)
Chinese(PDF, 3MB)
Contact: Project Manager, Lawrence Henriquez, Senior Civil Engineer — 650-829-6652